LatticeLog

  • Governance
  • Infrastructure
  • Markets
  • Analysis
  • Notes
  • Signals
  • Cycles
  • Learnings
  • Commentaries
  • Glossary
  • Home

Written by Nithinraj Kooneri

in Bifrost Systems
The Interconnection Queue — Fenrir Research
Bifrost Systems/Build/The Interconnection Queue
Fenrir Research · Bifrost Systems · Build / 03

The Interconnection Queue: The Line Everything Waits In

More power capacity is stuck waiting to connect to the US grid than exists on it today. This is the bottleneck the whole section keeps returning to — what it is, why it broke, and whether it’s being fixed.
Fenrir Research  ·  Jul 2026  ·  Yggdrasil Ledger / latticelog.in
◆ Hub piece — the reference other Bifrost posts point to

There was only one pass through the mountains, and so everything that wished to cross — armies, merchants, kings and thieves alike — came at last to the same narrow gate, and waited. The road beyond was empty. The road before it stretched back further than anyone could see.

Original epigraph, in the register of Tolkien’s mountain-pass verses
Section 01

What the Queue Actually Is

Before any power plant, wind farm, battery or data centre can plug into the grid, the grid operator has to study what connecting it would do — whether the surrounding wires can carry the extra load, and what upgrades would be needed to keep the system stable. That study, and the wait to receive it, is the interconnection queue. Nothing connects until it clears.

The study is not a formality. It determines the single most important number in a project’s budget: the cost of the network upgrades required to accommodate it — which can range from trivial to project-killing, and which the developer usually has to pay. Until the study is done, that cost is unknown, financing can’t close, and the project can’t proceed. The queue, in other words, is where a project’s economics are decided by someone other than its owner — and where most projects quietly die.

This piece is a hub: several other posts in Bifrost Systems — the AI demand shock, the colocation bypass, grid modernisation, second-life assets — all run into this same wall. Rather than re-explain it each time, this is the reference. If you understand the queue, you understand why so much of the infrastructure decade moves in slow motion.

Section 02

Why It Broke

For decades, the queue worked on a “first-come, first-served” basis: projects were studied one at a time, in the order they applied. That was fine when a handful of large power plants joined the grid each year. It fell apart when tens of thousands of smaller solar, wind and storage projects — cheap to propose, easy to file speculatively — flooded in at once.

Two design flaws turned a backlog into gridlock. First, cascading restudies: because each project’s upgrade costs depended on everything ahead of it, whenever a higher-placed project withdrew, everything behind it had to be studied again, resetting the clock. Second, speculative squatting: with little cost to hold a place in line, developers filed far more projects than they intended to build, clogging the queue with applications that were never real. The result is a queue full of “zombie” projects — occupying position, triggering restudies, and never intending to connect.

The Wait Has Quadrupled — PJM, Application to Operation
Approximate time from interconnection application to commercial operation in PJM, the largest US grid operator. Source: PJM / Energy Tech News reporting. From under two years in 2008 to more than eight by 2025.
Capacity in US Queues
~2,200 GW
More than the entire ~1,280 GW installed US fleet (S&P Global; LBNL)
Share Solar / Wind / Storage
~94%
The queue is overwhelmingly clean energy waiting to connect
Active Projects
10,000+
Most will withdraw before ever connecting
PJM Wait, 2025
8+ yrs
Up from under 2 years in 2008

The attrition is the part outsiders miss. The headline queue figure — 2,200 gigawatts, larger than everything currently plugged in — wildly overstates what will actually get built, because most of it never does.

Most of the Queue Never Connects
Illustrative attrition: of capacity that enters US interconnection queues, historically only around one project in five reaches commercial operation; the rest withdraw. In some regions the completion rate for battery storage has been closer to 1 in 10. Sources: Lawrence Berkeley National Laboratory queue studies; NYISO. Figures indicative.
Analyst Read — Read the Queue Net, Not Gross

The gross queue number is a trap. Because roughly four in five projects withdraw, a 2,200 GW queue does not mean 2,200 GW of coming supply — it means intense congestion around a much smaller pool of viable projects. The analytical work is separating the real from the speculative: a project with site control, financing and a completed study is worth far more than its queue position suggests, and a queue full of zombies is worth far less. Never take a queue figure at face value.

Section 03

The Fix — and Its Limits

In July 2023, FERC issued Order No. 2023, described by the commission as its largest interconnection reform in two decades. Its central move was to replace “first-come, first-served” with “first-ready, first-served.” Instead of studying projects one by one in filing order, grid operators now study them in clusters, all at once, and prioritise the ones that can demonstrate genuine commercial readiness — site control, financial deposits, real intent to build. The reform also imposes firm study deadlines, with financial penalties on grid operators that miss them.

The logic is sound: cluster studies stop the cascading restudies, and readiness requirements price the zombies out. But the rollout has been slow and uneven. FERC had to order PJM — the largest US grid operator, serving 65 million people — to redo its compliance plan in 2025 for not meeting the rule. Regions are now layering on their own expedited “fast lanes” for shovel-ready projects: PJM’s expedited track (accepted mid-2026) targets a roughly ten-month path to a signed agreement, and MISO and SPP have their own accelerated study processes. Even so, the backlog has kept growing, swollen by a wave of new solar-plus-storage applications.

The Reform in One Line

Order 2023 changed what wins a place in line: from who filed first, to who is actually ready to build.

That is a profound shift in who the queue rewards. Under the old rules, an early speculative filing beat a later serious project. Under the new rules, a well-capitalised developer with site control and financing can leapfrog the zombies. The reform doesn’t add grid capacity — only new wires do that — but it re-sorts the line in favour of the credible, which is its own kind of competitive advantage.

Section 04

Reading It Through the Frameworks

This is the canonical test of the primer’s central question, so it’s worth working through carefully — the logic recurs across the whole section.

The Fenrir Question, in Its Purest Form

Is the queue a structural moat, or a temporary bottleneck?

The answer is: both, for different people, and that is the whole trade. For a developer without a position, the queue is a bottleneck — a years-long tax on getting anything built. But for an incumbent that already holds a completed study, an interconnected brownfield site, or firm capacity at a connected point, the queue is a moat — a multi-year barrier no competitor can cross quickly at any price. The same wall that traps the outsider protects the insider. The durable value clusters with whoever is already through the gate.

That reframing explains several other pieces in this section at once. It is why colocation exists — the bypass is an attempt to avoid the queue entirely. It is why a retired coal or gas site is valuable beyond its hardware — the interconnection rights come with it. And it is why the relief technologies (reconductoring, grid-enhancing tech) are an investable theme in their own right: anything that moves more power through existing, already-connected wires sidesteps the queue by definition.

This wall shows up across the section: The Power-Compute Nexus (the demand piling into it) · Colocation & the Bypass Economy (routing around it) · Second-Life Infrastructure (inheriting the connection rights) · Grid Modernization & Undergrounding (relieving it without new lines).
Section 05

The Investment Map

If the scarce thing is an interconnected position, the map follows directly — and it splits cleanly into owning the scarcity versus owning its relief.

Interconnected Brownfield Sites
Own the scarcity
Retired or operating plant sites carry connection rights that now command a premium far above the hardware — the gate is already open.
Ready Developers
Winners of the re-sort
Well-capitalised developers who can meet the new readiness bar leapfrog the zombies — the reform favours the credible.
Grid-Enhancing Tech / Reconductoring
Own the relief
Moving more power through existing wires sidesteps the queue entirely — a distinct, fast-growing relief trade.
Transmission Builders
The real fix, slowly
Only new lines add genuine capacity, but they take a decade to permit — durable demand, glacial delivery.
Battery Storage Developers
Caught in the line
Storage dominates the queue but suffers the worst completion rates — queue position is a poor proxy for delivered projects.
Speculative Filers
Priced out
The readiness requirements are designed to eliminate them — the zombie-filing model is ending.
Analyst Read — The Position Is the Asset

In a queue-constrained grid, the interconnection position is frequently worth more than the project attached to it. That is why deals increasingly change hands for the connection rights alone, and why the reform — by making those rights harder to acquire speculatively — raises the value of the ones that already exist. Own the position, or own the technology that makes the position unnecessary. Owning neither means waiting in a line that most projects never leave.

Bottom Line

The interconnection queue is the single most important bottleneck in the Western power system, and the quiet reason so much of the infrastructure build-out moves slowly. More capacity waits in it than exists on the grid — but four in five of those projects will never connect, so the gross number misleads more than it informs. The reform re-sorts the line toward the ready; it does not shorten it.

Hold the one idea this hub exists to establish: the queue is a bottleneck for outsiders and a moat for insiders, and the durable value sits with whoever is already through the gate — or who sells the means to avoid it. Every time another Bifrost piece runs into this wall, that is the lens to bring.

The tolls of the pass made its keepers richer than the kings whose armies waited there. They had built nothing, grown nothing, mined nothing. They had simply arrived at the gate first, and never left it.

Original epigraph, in the register of Tolkien’s mountain-pass verses
Bifrost Systems · Build Thread
← Previous
Colocation & the Bypass Economy
The attempt to route around the queue this piece explains
Next →
Cooling & Thermal Management
The thermal half of the AI build-out
Sources & Notes
FERC Order No. 2023 (issued July 28, 2023) and subsequent compliance proceedings; FERC direction to PJM to revise its compliance plan (July 2025) and acceptance of PJM’s expedited interconnection track (2026); MISO / SPP Expedited Resource Addition Study processes. Queue scale, composition and wait-time data: Lawrence Berkeley National Laboratory (“Queued Up” series); S&P Global Commodity Insights; PJM, MISO, NYISO reporting; Energy Tech News; Utility Dive; National Law Review, K&L Gates and Troutman Pepper Locke summaries of Order 2023. Attrition and completion rates are historical and indicative; they vary by region and technology. All framing and conclusions are Fenrir Research’s own.
This analysis is for informational purposes only. Not investment advice. Fenrir Research is a division of Yggdrasil Ledger (latticelog.in).
←Colocation & the Bypass Economy
Cooling & Thermal Management→

Comments

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

More posts

  • The Health Case That Closes

    July 28, 2026
  • The Border Adjustment Problem

    July 28, 2026
  • The Young Fleet

    July 28, 2026
  • Committed Emissions

    July 28, 2026

LatticeLog

Structural research across markets, infrastructure, climate, and the systems that connect them. Published under Fenrir Research, a division of Yggdrasil Ledger.

  • Blog
  • About
  • FAQs
  • Authors

Twenty Twenty-Five

Designed with WordPress